Glossary
NERC compliance terms, defined plainly.
The acronyms behind PRC, FAC and CIP compliance, especially the new IBR standards, in one place. Where a term comes from a specific requirement, we say which.
- BES — Bulk Electric System
- The transmission elements and generating resources (generally 100 kV and above, with defined inclusions and exclusions) that NERC Reliability Standards protect.
- BCSI — BES Cyber System Information
- Information about a BES Cyber System that could be used to gain unauthorized access or pose a security threat. Protected under CIP-011; provisioned access managed under CIP-004-7 R6.
- BES Cyber System
- One or more BES Cyber Assets grouped to perform a reliability function. Categorized as high, medium or low impact under CIP-002.
- CAP — Corrective Action Plan
- A documented list of actions and a timetable to fix an identified problem, such as an IBR performance issue under PRC-030-1 R3 or a recording failure under PRC-028-1 R8.
- Category 2 IBR
- A non-BES inverter-based resource with ≥ 20 MVA aggregate nameplate connected at ≥ 60 kV, whose owners and operators NERC registered as GOs and GOPs effective May 15, 2026. See our IBR guide.
- CEA — Compliance Enforcement Authority
- NERC or the Regional Entity (or another designated body) that monitors and enforces compliance.
- CIP Senior Manager
- The single named senior manager accountable for an entity's CIP program, required by CIP-003 R3.
- CMEP — Compliance Monitoring and Enforcement Program
- NERC's process for audits, spot checks, self-reports and enforcement of Reliability Standards.
- COMTRADE — IEEE C37.111
- The Common Format for Transient Data Exchange: a .cfg header and .dat data file pair used by relays and recorders. One of the formats PRC-028-1 accepts for fault recording data.
- DDR — Dynamic disturbance recording
- Continuous, lower-rate recording of system quantities for minutes to hours. PRC-028-1 requires ≥ 960 samples/s input and ≥ 60 records/s output at each main power transformer.
- Deterministic validation
- Compliance logic written as explicit rules, so identical inputs always produce identical results with the calculation shown. The opposite of a probabilistic model's answer.
- DFR — Digital fault recorder
- A device that captures high-resolution waveforms around a trigger. Its records are a common input to PRC-028 and PRC-030 work.
- DME — Disturbance monitoring equipment
- Devices that record SER, fault and dynamic disturbance data.
- Facility Rating
- The maximum or minimum voltage, current, frequency or power flow a Facility can carry, set by its most limiting series equipment. Governed by FAC-008.
- FR — Fault recording
- Triggered, high-resolution recording of voltages and currents. PRC-028-1 requires ≥ 2 cycles of pre-trigger and ≥ 2.0 s total length.
- GO / GOP — Generator Owner / Generator Operator
- NERC functional registrations for entities that own or operate generating facilities.
- GSU / MPT — Generator step-up / main power transformer
- The transformer connecting a plant to the transmission system. PRC-024 and PRC-029 measure voltage at its high side.
- IBR — Inverter-based resource
- A generating or storage resource connected through power electronics: solar PV, Type 3 and 4 wind, battery storage.
- Momentary cessation
- An inverter stopping current injection during a voltage disturbance without disconnecting. Prohibited in the PRC-029-1 must-ride-through zone.
- Most limiting element
- The series equipment with the lowest rating in a Facility, which sets the Facility Rating. FAC-008 R8 requires identifying it on request.
- No-trip zone
- The voltage–time or frequency–time region in PRC-024 Attachments 1 and 2 where protection must not trip a unit. It ends at 4 seconds for voltage.
- PSMP — Protection System Maintenance Program
- The program PRC-005 R1 requires, defining maintenance methods, activities and intervals for each component type.
- Regional Entity
- One of the six organizations (MRO, NPCC, RF, SERC, Texas RE, WECC) that audit and enforce NERC standards under delegation.
- Ride-through
- Staying connected and continuing to support the grid during a voltage or frequency excursion. Required of IBRs by PRC-029-1.
- RoCoF — Rate of change of frequency
- How fast system frequency is moving, in Hz/s. PRC-029-1 requires ride-through when |RoCoF| ≤ 5 Hz/s.
- RSAW — Reliability Standard Audit Worksheet
- The worksheet auditors use to assess compliance with a standard, which entities often pre-populate with their evidence.
- SER — Sequence of events recording
- Time-stamped records of breaker and status changes. Required for IBRs by PRC-028-1 R1 and delivered as CSV.
- Unresolved Maintenance Issue
- A deficiency found during PRC-005 maintenance that can't be fixed during that activity. R5 requires demonstrated efforts to correct it.
- VSL / VRF — Violation Severity Level / Violation Risk Factor
- How badly a requirement was missed, and how much risk the requirement addresses. Together they drive penalty ranges.
Definitions are our summaries. The NERC Glossary of Terms Used in Reliability Standards is authoritative.