Who is Category 2
A Category 2 IBR is a non-BES inverter-based resource that has or contributes to an aggregate nameplate capacity of 20 MVA or more, connected through a system designed primarily to deliver that capacity to a common point of connection at 60 kV or above. NERC extended GO and GOP registration to these resources after FERC directed it to close the reliability gap, and set an effective registration date of May 15, 2026.
By April 20, 2026 NERC had sent notification letters to 449 entities covering 531 facilities. Many are plants that were never registered before, owned by organizations that have never written an RSAW.
The three standards written for IBRs
PRC-028-1: record it. SER, fault recording and continuous dynamic disturbance recording, time-synced to UTC, retrievable for 20 days. Without this data the other two standards can't be met.
PRC-029-1: ride through it. Stay connected and supportive through defined voltage and frequency excursions, with RoCoF up to 5 Hz/s. Legacy hardware that genuinely can't comply needs documented R4 evidence within 12 months.
PRC-030-1: explain it. Find every unexpected output loss (≥ 20 MW and ≥ 10% of nameplate in 4 seconds, or a complete loss), analyze it within 90 days, and fix what you find.
They work as a chain: PRC-028 produces the recordings, PRC-030 screens them for events, and PRC-029 is the yardstick for whether the plant performed. Software that handles all three on the same data is the difference between one workflow and three spreadsheets.
Dates
| May 15, 2026 | Category 2 GO/GOP registration effective |
|---|---|
| October 1, 2026 | PRC-029-1 and PRC-030-1 effective in the U.S. (both phased in) |
| By October 2027 | PRC-029-1 R4 hardware-limitation documentation due |
| Ongoing | PRC-028-1 phased implementation per its plan |
The full list, with CIP dates through 2029, is on our NERC compliance calendar.
The first 90 days
- Inventory and one-line. Every inverter, collector breaker, MPT, reactive device and recorder, with nameplates. Everything else is built on this.
- Recorder reality check. Compare what your DFRs and inverters actually record (channels, record length, sample rates, clock accuracy) against PRC-028-1.
- Write the PRC-030 R1 process, then prove it runs. A procedure alone isn't evidence. Keep the screening results for every record, including the excluded ones and why.
- Settings review. Ride-through and momentary-cessation settings on every inverter model against PRC-029-1, with OEM documentation.
- Decide on R4 early. If a legacy unit can't comply and only hardware replacement would fix it, the documentation package takes months. The deadline is October 2027.
- Start CIP-002. Categorize your BES Cyber Systems; it decides which other CIP requirements apply.
Where data phleet fits
We automate PRC-028-1, PRC-029-1, PRC-030-1, CIP-002 and asset inventory on the same data, so a new registrant gets a working compliance program instead of a stack of templates. Talk to us about your fleet →
Category 2 IBR questions
What is a Category 2 inverter-based resource?
A non-BES inverter-based resource (solar, wind, battery storage) that has or contributes to an aggregate nameplate capacity of 20 MVA or more, connected through a system designed primarily to deliver that capacity to a common point of connection at 60 kV or above. NERC extended Generator Owner and Generator Operator registration to these resources; the effective registration date was May 15, 2026.
Which IBR-specific standards apply to Category 2 resources?
PRC-028-1 (disturbance monitoring and recording), PRC-029-1 (frequency and voltage ride-through) and PRC-030-1 (unexpected IBR event mitigation) all include non-BES IBRs at the 20 MVA / 60 kV threshold, with phased implementation. Registration as a GO or GOP also brings a set of existing standards into scope; NERC publishes the applicable list for Category 2 registrants.
How many entities were registered as Category 2?
As of April 20, 2026, NERC had sent registration notification letters to 449 Category 2 GO/GOP entities representing 531 Category 2 IBR facilities, according to pv magazine's reporting.
What should a newly registered IBR owner do first?
Get an accurate inventory and one-line, confirm what your disturbance recorders actually capture against PRC-028-1, document an R1 event-screening process for PRC-030-1 and prove it runs, review inverter ride-through and momentary-cessation settings against PRC-029-1, and decide by October 2027 whether any legacy unit needs an R4 hardware-limitation exemption.
New to NERC? Start with one plant.