PRC-005-6 Automated today

Protection System, Automatic Reclosing, and Sudden Pressure Relaying Maintenance

PRC-005-6 requires Transmission Owners, Generator Owners and Distribution Providers to maintain their Protection Systems, Automatic Reclosing and Sudden Pressure Relaying, and prove it. You need a Protection System Maintenance Program (R1). If you use performance-based intervals, follow Attachment A (R2, R4). If you use time-based intervals, meet the minimum activities and maximum intervals in the standard's tables (R3). And you must show efforts to correct Unresolved Maintenance Issues (R5).

Key facts
StatusIn effect
Applies toTransmission Owners, Generator Owners, Distribution Providers
ScopeProtection Systems, Automatic Reclosing and Sudden Pressure Relaying that affect the BES
IntervalsTime-based per Tables 1-1 through 1-5, 2, 3, 4-1 through 4-3 and 5, or performance-based per Attachment A
RelatedPRC-024, asset inventory

What PRC-005-6 requires

Our plain-language summary of each requirement. The standard's text governs.

R1

Protection System Maintenance Program

Establish a PSMP that identifies the maintenance method for each component type and the activities and intervals that apply.

R2

Performance-based intervals

If you use performance-based intervals, establish and maintain them using the Attachment A procedure.

R3

Time-based maintenance

Maintain components in time-based programs to the minimum activities and maximum intervals in the standard's tables.

R4

Follow your performance-based program

Implement and follow the PSMP for components in performance-based programs.

R5

Unresolved Maintenance Issues

Demonstrate efforts to correct identified Unresolved Maintenance Issues.

Evidence an auditor will ask for

  • The PSMP itself, with the method for each component type
  • Maintenance records proving every component met its interval, including relays, CTs/PTs, DC supply and batteries, communications, and auxiliary relays
  • For performance-based programs, the Attachment A population and countable-event analysis
  • Records of Unresolved Maintenance Issues and the corrective work

Where teams get caught

  • Components that exist in the field but not in the PSMP inventory
  • Battery and DC supply records, which can take the longest to assemble at large sites
  • Intervals calculated from the wrong date after a partial test
  • Evidence spread across CMMS exports, spreadsheets and paper

What data phleet does for PRC-005-6

  • Reads one- and three-line diagrams, maintenance records, settings sheets and nameplates directly
  • Builds the component inventory and matches every component to its PSMP interval and latest maintenance record
  • Flags overdue, missing and undocumented maintenance, with the source record
  • Ships each run as XLSX, PDF, a gaps report and a pre-filled RSAW
data phleet PRC-005-6 report details screen
PRC-005-6 report details in a customer environment. Each run ships as an XLSX, a PDF, a gaps report and a pre-filled RSAW.

The first automated PRC-005 check →

PRC-005-6 questions

Who does PRC-005-6 apply to?

Transmission Owners, Generator Owners and Distribution Providers, for Protection Systems, Automatic Reclosing and Sudden Pressure Relaying that affect the reliability of the BES.

What's the difference between time-based and performance-based maintenance under PRC-005?

Time-based programs follow the fixed maximum intervals in the standard's tables. Performance-based programs set intervals from the actual failure performance of a component population, using the procedure in Attachment A.

See your PRC-005-6 evidence, organized.

Book 30 minutes. Bring one site's records and we'll surface the evidence live, show you the gaps and walk through the reports.