NERC compliance calendar · updated November 12, 2026
Every NERC date that matters, 2026 to 2029.
U.S. effective dates for NERC Reliability Standards and the IBR registration milestones, taken from NERC's own enforcement bulletins and standards, plus the recurring compliance clocks that catch teams out. Free to use and link to.
Effective dates
Past dates are greyed; the next one is highlighted. "Phased in" means the implementation plan spreads obligations over later dates too. Check the plan for your facilities.
Want this as a reminder feed? Ask us and we'll add your team to our dates email.
- CIP-003-9 Security management controls; adds vendor electronic remote access controls for low impact BES Cyber Systems
- MOD-026-2 Verification and validation of dynamic models and data (phased in)
- MOD-033-3 Steady-state and dynamic system model validation
- TPL-008-1 Transmission planning for extreme temperature events (phased in)
- Category 2 IBR Effective registration date for Category 2 Generator Owners and Operators: non-BES IBRs ≥ 20 MVA at ≥ 60 kV
- CIP-012-2 Communications between control centers
- PRC-029-1 IBR frequency and voltage ride-through (phased in)
- PRC-030-1 Unexpected IBR event mitigation (phased in)
- PRC-024-4 Frequency and voltage protection settings for synchronous generators, Type 1 and 2 wind, synchronous condensers
- TOP-003-7 TOP and BA data specification and collection
- BAL-007-1.1 Near-term energy reliability assessments
- PRC-029-1 R4 Hardware-limitation documentation for legacy IBRs due, 12 months after the effective date
- MOD-032-2 Data for power system modeling and analysis (phased in)
- CIP-002-8 BES Cyber System categorization
- CIP-003-10 Security management controls
- CIP-004-8 Personnel and training
- CIP-005-8 to CIP-011-4.1 Electronic security perimeters, physical security, system security, incident response, recovery, configuration change management, information protection
- CIP-013-3 Supply chain risk management
- CIP-015-1 Internal network security monitoring
- IRO-010-6 RC data specification and collection
- TOP-003-8 TOP and BA data specification and collection
- CIP-003-11 Security management controls
The clocks inside the standards
These start on an event, not a calendar date, which is why they get missed.
| Requirement | Clock | What it governs |
|---|---|---|
| PRC-030-1 R2 | 90 calendar days | to analyze a qualifying IBR output change, from the event or an RC/BA/TOP request |
| PRC-030-1 R3 | 60 calendar days | after the R2 analysis, to send a CAP or technical justification to the RC, BA and TOP |
| PRC-028-1 R7 | 20 days / 15 days | data retrievable for 20 calendar days; provided within 15 days of a request |
| PRC-028-1 R8 | 90 calendar days | to restore a failed SER, FR or DDR recording capability, or submit a CAP |
| PRC-024 R4 | 60 calendar days | to give frequency and voltage settings to the PC or TP after a request or a change |
| PRC-019-2 | 5 years / 90 days | coordination at least every five calendar years, and within 90 days of a change that affects it |
| CIP-002-5.1a R2 | 15 calendar months | review BES Cyber System identifications; CIP Senior Manager approval |
| CIP-003-9 R1 | 15 calendar months | review and CIP Senior Manager approval of cyber security policies |
| CIP-003-9 R3 | 30 calendar days | to document a change of CIP Senior Manager |