PRC-019-2 Automated today

Coordination of Generating Unit or Plant Capabilities, Voltage Regulating Controls, and Protection

PRC-019-2 requires that a generator's voltage regulating controls, limiters, equipment capability and protection settings are coordinated, so limiters act before protection and protection still prevents damage. Generator Owners and Transmission Owners must do the coordination at least every five calendar years (R1), and again within 90 days of any system, equipment or setting change that affects it (R2).

Key facts
StatusIn effect
Applies toGenerator Owners and Transmission Owners: units or synchronous condensers > 20 MVA, and plants > 75 MVA aggregate at a common bus (including I4 dispersed resources)
Interval (R1)At most every five calendar years
Change trigger (R2)Within 90 calendar days of identifying or implementing a change that affects coordination
RelatedPRC-024, PRC-025-2, MOD-025-2

What PRC-019-2 requires

Our plain-language summary of each requirement. The standard's text governs.

R1

Coordinate, at least every five years

Coordinate the voltage regulating system controls, including in-service limiters and protection functions, with the equipment capabilities and Protection System settings. In-service limiters must operate before the Protection System to avoid unnecessary disconnection, and protection must still operate to limit damage when conditions exceed equipment capability or stability limits.

R2

Re-coordinate after changes

Within 90 calendar days after identifying or implementing system, equipment or setting changes that affect the R1 coordination, perform the coordination again.

Evidence an auditor will ask for

  • The coordination study: capability curve, limiter settings (OEL, UEL, V/Hz) and relay settings on one set of axes
  • Dated proof the study was done within five years
  • Change records and proof of re-coordination within 90 days

Where teams get caught

  • Limiter curves that have to be reconstructed because AVR settings were never captured
  • Exciter or relay replacements that never trigger the 90-day R2 re-coordination
  • Capability data that doesn't match the latest MOD-025 test

What data phleet does for PRC-019-2

  • Gathers AVR, limiter, relay settings and capability data per unit, in one place for the coordination study
  • Flags missing settings and capability data before your engineers start the study
  • Tracks the five-year coordination cycle and packages the study and its evidence for the audit
  • Spots settings-file changes and starts the 90-day R2 clock, so it never slips
PRC-019-2 R1 coordination on the P-Q planeillustrative 100 MW unit
PRC-019-2 limiter and protection coordination Generator reactive capability curve with the over-excitation limiter inside the upper curve, the under-excitation limiter inside the lower curve, and the loss-of-field relay characteristic outside it, so limiters act before protection and protection acts before damage. capabilityOELUELcapability40 loss of field UEL margin to capability: 7 MVAr min 40 element outside capability: limiter acts first -60-300+30+600255075100MVArMW
limiter → protection → damage, in that ordercoordinated

Introducing the automated PRC-019-2 check →

PRC-019-2 questions

How often is a PRC-019-2 coordination study required?

At least once every five calendar years, and within 90 calendar days of any system, equipment or setting change that affects the coordination.

Does PRC-019-2 apply to inverter-based resources?

It can. Applicable Facilities are individual units or synchronous condensers over 20 MVA connected to the BES, and plants over 75 MVA aggregate at a common bus, which expressly includes dispersed power producing resources (such as solar and wind) identified under BES Inclusion I4.