PRC-019-2 Automated today
Coordination of Generating Unit or Plant Capabilities, Voltage Regulating Controls, and Protection
PRC-019-2 requires that a generator's voltage regulating controls, limiters, equipment capability and protection settings are coordinated, so limiters act before protection and protection still prevents damage. Generator Owners and Transmission Owners must do the coordination at least every five calendar years (R1), and again within 90 days of any system, equipment or setting change that affects it (R2).
| Status | In effect |
|---|---|
| Applies to | Generator Owners and Transmission Owners: units or synchronous condensers > 20 MVA, and plants > 75 MVA aggregate at a common bus (including I4 dispersed resources) |
| Interval (R1) | At most every five calendar years |
| Change trigger (R2) | Within 90 calendar days of identifying or implementing a change that affects coordination |
| Related | PRC-024, PRC-025-2, MOD-025-2 |
What PRC-019-2 requires
Our plain-language summary of each requirement. The standard's text governs.
Coordinate, at least every five years
Coordinate the voltage regulating system controls, including in-service limiters and protection functions, with the equipment capabilities and Protection System settings. In-service limiters must operate before the Protection System to avoid unnecessary disconnection, and protection must still operate to limit damage when conditions exceed equipment capability or stability limits.
Re-coordinate after changes
Within 90 calendar days after identifying or implementing system, equipment or setting changes that affect the R1 coordination, perform the coordination again.
Evidence an auditor will ask for
- The coordination study: capability curve, limiter settings (OEL, UEL, V/Hz) and relay settings on one set of axes
- Dated proof the study was done within five years
- Change records and proof of re-coordination within 90 days
Where teams get caught
- Limiter curves that have to be reconstructed because AVR settings were never captured
- Exciter or relay replacements that never trigger the 90-day R2 re-coordination
- Capability data that doesn't match the latest MOD-025 test
What data phleet does for PRC-019-2
- Gathers AVR, limiter, relay settings and capability data per unit, in one place for the coordination study
- Flags missing settings and capability data before your engineers start the study
- Tracks the five-year coordination cycle and packages the study and its evidence for the audit
- Spots settings-file changes and starts the 90-day R2 clock, so it never slips
PRC-019-2 questions
How often is a PRC-019-2 coordination study required?
At least once every five calendar years, and within 90 calendar days of any system, equipment or setting change that affects the coordination.
Does PRC-019-2 apply to inverter-based resources?
It can. Applicable Facilities are individual units or synchronous condensers over 20 MVA connected to the BES, and plants over 75 MVA aggregate at a common bus, which expressly includes dispersed power producing resources (such as solar and wind) identified under BES Inclusion I4.
Other standards we cover
- PRC-005-6 Protection System Maintenance
- PRC-024-4 Frequency and Voltage Protection Settings
- PRC-025-2 Generator Relay Loadability
- PRC-028-1 IBR Disturbance Monitoring
- PRC-029-1 IBR Ride-through
- PRC-030-1 Unexpected IBR Event Mitigation
- FAC-008-5 Facility Ratings
- CIP-002-5.1a BES Cyber System Categorization
- CIP-003-9 Security Management Controls
- CIP-004-7 Personnel and Training
- Inventory Asset Inventory
See your PRC-019-2 evidence, organized.
Book 30 minutes. Bring one site's records and we'll surface the evidence live, show you the gaps and walk through the reports.