When a solar, wind or storage plant unexpectedly drops a large share of its output during a grid disturbance, someone has to find out why and fix it. That's PRC-030-1, Unexpected Inverter-Based Resource Event Mitigation, effective in the U.S. on October 1, 2026 with phased implementation.
Correction: an earlier version of this announcement described PRC-030-1 as a disturbance monitoring equipment standard. Recording requirements are in PRC-028-1; PRC-030-1 covers identifying, analyzing and mitigating unexpected IBR output changes.
What it requires
- R1, identify: have a process to find changes in real power output that are a complete loss of output, or at least 20 MW and at least 10% of gross nameplate, within 4 seconds. Changes caused by energy-source variation (irradiance, wind), dispatch, ramping, outages or testing, or by a transmission or collector loss that disconnects the IBR by configuration, are excluded.
- R2, analyze: within 90 calendar days, determine what happened and whether the IBR's performance can be improved.
- R3, plan: within 60 days of the analysis, develop a corrective action plan or a technical justification for not changing anything, and send it to the RC, BA and TOP.
- R4, implement: carry out the CAP, update it as things change, and notify when it's done.
Why automate it
R1 is a screening problem at scale. Every disturbance record from every plant has to be checked against the threshold and the exclusions, and the screening itself is evidence, including for records that turn out not to qualify. Done by hand, it gets done late or not at all, and the 90-day clock is already running.
What our check does
- Reads each COMTRADE record and plant data as it arrives
- Computes the output change in the 4-second window against both thresholds
- Tests the exclusions with irradiance or wind data, dispatch and topology
- Starts the R2 and R3 clocks and tracks them to the CAP
- Produces the evidence package for each event, qualifying or not
At RE+ 2026 we ran it live: a button on a real SEL-710 relay trips a simulated 100 MW plant, and data phleet screens the disturbance record against R1 on its own.
A new partnership
We also announced a partnership with a leading consulting firm in the electric power industry, which runs data phleet across hundreds of customer environments.