PRC-029-1 · R4 hardware-limitation exemption
When is the PRC-029-1 exemption deadline?
By October 1, 2027 in the U.S.: 12 months after PRC-029-1 took effect. Here's who qualifies, what the documentation must include, who gets a copy and the clocks that follow.
Checked against the NERC standard on November 12, 2026.
The short answer
PRC-029-1 R4 exemption documentation is due no later than 12 months after the standard's effective date. PRC-029-1 became effective in the United States on October 1, 2026, so the documentation, and copies of it to every required entity, are due by October 1, 2027. Only IBRs that were in service by the effective date qualify, and only for limitations that physically replacing hardware would fix.
| Deadline | No later than 12 months after the PRC-029-1 effective date: by October 1, 2027 in the U.S. (R4.1, R4.2) |
|---|---|
| Who qualifies | Generator Owners with an IBR in service by the effective date that has a known hardware limitation preventing it from meeting R1–R3 |
| Send copies to | Planning Coordinator, Transmission Planner, Transmission Operator, Reliability Coordinator and the Compliance Enforcement Authority (R4.2) |
| Questions back | Answer requests for more information within 90 days (R4.2.1) |
| After acceptance | Forward the CEA's acceptance to the PC, TP, TOP and RC within 90 days (R4.2.2) |
| Hardware replaced | Notify the PC, TP, TOP and RC within 90 days; the exemption ends (R4.3) |
What the documentation must include
R4.1 lists five items. Missing any of them is the easiest way to fail, because CEA acceptance is a check that all five are there.
- Identifying information for the IBR: name and facility number (R4.1.1).
- Which ride-through requirements it can't meet, and what the hardware can actually do (R4.1.2).
- The specific piece or pieces of hardware causing the limitation (R4.1.3).
- Technical documentation showing the limitation needs physical hardware replacement and can't be remedied by software updates or setting changes (R4.1.4).
- Any plans to remedy it, such as an estimated replacement date (R4.1.5).
The measure (M4) says OEM damage curves are one acceptable form of evidence for a hardware limitation.
Who gets a copy
Send the package to every associated Planning Coordinator, Transmission Planner, Transmission Operator and Reliability Coordinator, and to the Compliance Enforcement Authority (NERC or your Regional Entity), within the same 12-month window. Material the inverter OEM considers proprietary goes only to the CEA.
Keep proof of each transmittal. M4 accepts emails, meeting minutes, agreements and similar records, but you need one for every entity, not just the CEA.
The clocks after you submit
- 90 days to answer any request for more information from the PC, TP, TOP, RC or CEA (R4.2.1).
- 90 days from receiving the CEA's acceptance to send a copy to the PC, TP, TOP and RC (R4.2.2).
- 90 days from replacing the hardware that caused the limitation to document and communicate the change. The exemption for those criteria then ends (R4.3, R4.3.1).
A practical schedule
This is our suggestion, not a NERC requirement. Working back from October 1, 2027:
- Now: list every IBR in service by October 1, 2026, with inverter and plant-controller models and firmware versions.
- Next 3 months: ask each OEM in writing whether the model can meet Attachments 1 and 2 with current or available firmware and settings. A firmware path rules out R4.
- By mid-2027: for the units that can't, collect the OEM technical documentation and damage curves, and have your engineers confirm the gap.
- By September 2027: assemble the five-item package per IBR and send it to all five entity types, with the proprietary parts to the CEA only.
- After that: track the 90-day clocks for questions, acceptance and any hardware replacement.
Where data phleet fits
The engineering call, whether a limitation is real and hardware-only, belongs to your engineers and the OEM. data phleet handles the compliance side: it inventories your IBRs against PRC-029-1 applicability, keeps the inverter models and settings records in one place, assembles each R4 package, and tracks every transmittal and 90-day clock so nothing slips. More on the standard itself: PRC-029-1 requirements, evidence and automation.
Related questions
Can a new IBR use the PRC-029-1 R4 exemption?
No. R4 only covers IBRs that are in service by the effective date of PRC-029-1. A plant that comes online later has to meet the ride-through requirements as built.
Does a firmware update or settings change count as a hardware limitation?
No. R4.1.4 requires technical documentation showing the limitation is due to hardware that would have to be physically replaced, and that it can't be fixed by software updates or setting changes. If the inverter OEM has a firmware fix, the exemption doesn't apply.
Does CEA acceptance mean the exemption is approved?
The standard defines acceptance narrowly: acceptance by the Compliance Enforcement Authority verifies that the submission includes all the information listed in R4.1. You then have 90 days to send a copy of the acceptance to your Planning Coordinator, Transmission Planner, Transmission Operator and Reliability Coordinator (R4.2.2).
What happens to the exemption when we replace the inverters?
The exemption for those ride-through criteria ends when the hardware causing the limitation is replaced (R4.3.1). You have 90 days from the hardware change to document it and tell your PC, TP, TOP and RC (R4.3).
Do we have to share the OEM's proprietary documents with everyone?
No. Material the original equipment manufacturer considers proprietary only has to go to the CEA. The PC, TP, TOP and RC get the rest of the R4.1 package.
Is there a second chance after the deadline?
R4 has no provision for documentation submitted after the 12-month window. If you think a plant needs an exemption, treat October 2027 as a hard stop and talk to your Regional Entity early.
Track every R4 package and clock.