PRC-030-1 · R1 event trigger
What counts as a PRC-030-1 event?
A complete loss of output, or a drop of at least 20 MW and 10% of gross nameplate within 4 seconds, minus four exclusions. Worked examples, the evidence each exclusion needs and the clocks that follow.
Checked against the NERC standard on November 12, 2026.
The short answer
A PRC-030-1 event is any complete loss of a plant's output, or any change in real power output of at least 20 MW and at least 10% of the plant's gross nameplate rating, occurring within a 4-second period. Four kinds of change are excluded: energy-source variation (irradiance, wind), planned operation, a grid configuration that disconnects the plant, and a misoperation handled under PRC-004. Every qualifying event starts a 90-day analysis clock.
| Trigger (R1) | Complete facility loss of output, or ΔP ≥ 20 MW and ≥ 10% of gross nameplate within a 4-second period |
|---|---|
| Threshold basis | Gross nameplate rating of the plant, not output at the time |
| Also triggered by | An RC, BA or TOP request after it identifies a Disturbance and a change in your IBR's output (R2) |
| Analysis clock | 90 calendar days from the event or the request (R2) |
| Corrective action clock | 60 calendar days after the analysis, if it finds an issue needing correction (R3) |
Worked examples
The two thresholds work together. Both must be met, unless the plant loses all of its output.
| Gross nameplate | Change | % of nameplate | Qualifies? |
|---|---|---|---|
| 100 MW | 15 MW in 3 s | 15% | No: under 20 MW |
| 300 MW | 25 MW in 2 s | 8.3% | No: under 10% |
| 150 MW | 25 MW in 2 s | 16.7% | Yes, unless excluded |
| 150 MW | 40 MW over 60 s, never 20 MW in any 4 s | 26.7% | No: not within 4 s |
| 50 MW | Trips from 12 MW to zero | Complete loss | Yes, unless excluded |
The "4-second period" is why screening has to look at high-resolution recordings. Hourly or one-minute SCADA averages can hide a qualifying drop. We screen with a sliding 4-second window across every disturbance record; that's our practice, and the safest reading of R1.
The four exclusions, and the evidence each needs
R1 excludes these changes. An exclusion isn't automatic: you need records that show why the change didn't count.
| Exclusion | What R1 says | Evidence to keep |
|---|---|---|
| Energy source | Changes from intermittent primary energy source availability, such as variation in wind speed or solar irradiance | Met-station irradiance or wind data for the same seconds |
| Planned operation | Resource dispatch, resource ramping, planned outages or planned resource testing | Dispatch instructions, AGC or ramp logs, outage and test records |
| Grid configuration | A transmission or collection-system loss that, by configuration, disconnects the IBR | Breaker and SER records, one-line showing the radial connection |
| Misoperation | A reduction due solely to a Protection System Misoperation being analyzed and corrected under PRC-004 | The PRC-004 misoperation record and its corrective action |
What happens after a qualifying event
- Within 90 calendar days (R2): determine the root cause, document ride-through performance including reactive power response, decide whether corrective action is needed, and check whether the root cause applies to your other IBR facilities.
- Within 60 calendar days of the analysis (R3): if a performance issue needs correcting, produce a Corrective Action Plan or a technical justification and send it to your RC, BA and TOP.
- Until it's done (R4): implement the CAP, update it if actions or timetables change, and notify the RC.
M1 also expects the documented detection process itself, proof that it runs, the actual data recordings and the plant's gross nameplate rating. A written procedure with no screening results behind it is a common gap.
Where data phleet fits
data phleet screens every COMTRADE disturbance record your plant produces against the R1 thresholds, using gross nameplate from your asset record. It flags each qualifying event, attaches the irradiance or other records behind any exclusion, and starts the R2 and R3 clocks. The root-cause analysis stays with your engineers; data phleet gives them the drop magnitude, percentage, time window and source files in one place, and keeps the screening record that proves R1 runs. Step-by-step method: how to screen COMTRADE records for PRC-030-1. More on the standard: PRC-030-1 requirements, evidence and automation.
Related questions
Do both the 20 MW and the 10% thresholds have to be met?
Yes. R1 says changes that are at least 20 MW and at least 10% of the plant's gross nameplate rating. A 25 MW drop at a 300 MW plant (8.3%) doesn't qualify; neither does a 15 MW drop at a 100 MW plant (15%, but under 20 MW). A complete loss of output always qualifies.
Is the 10% based on nameplate or on output at the time?
Gross nameplate rating. R1 uses 10% of the plant's gross nameplate rating, and M1 lists identification of the gross nameplate rating as required evidence.
Is a cloud passing over a solar plant a PRC-030-1 event?
No. Changes associated with intermittent primary energy source availability, such as variation in solar irradiance or wind speed, are excluded. Keep the irradiance or wind data that shows it, because an auditor will ask how you knew.
Does a relay misoperation count?
Not if the real power reduction is due solely to a Protection System Misoperation that is being analyzed and corrected under PRC-004. If something else contributed, it's back in scope.
Can a PRC-030-1 analysis be required without an R1 event?
Yes. R2 also starts when your Reliability Coordinator, Balancing Authority or Transmission Operator identifies a Disturbance and a change in your IBR's output and asks you for an analysis. The 90-day clock runs from the request.
How long do we have to analyze an event?
90 calendar days from the event or the request (R2). If the analysis finds a performance issue needing correction, you then have 60 calendar days to produce a Corrective Action Plan or a technical justification (R3).
See which of your events qualify.
Bring a month of a plant's disturbance records. We'll screen them against R1 live and show you what qualifies, what's excluded and why.